The Massey Tunnel, 1959 to now

It opened in 1959 for $16.6M. Replacing it has been announced, priced, cancelled and re-planned ever since. Here is every step, with where each number comes from.

$16.6M
to build it
Opened May 23, 1959
$8.5B
budget to replace it
About 510 times the original, before inflation
$581M
spent on the new tunnel
To Jun 30, 2026, the last official report
3
times the plan changed course
The bridge halted in 2017 and dropped in 2018; the tunnel's contractor dropped in 2026

Where it stands, Nov 14, 2026

As of November 14, 2026, early construction on the eight-lane Fraser River Tunnel Project continues under existing contracts, work the Province said would create about 200 jobs in 2026, but the main construction contracts have not been awarded and the environmental assessment certificate has not been issued. The Conservative Party of BC, which won the October 24 election after pledging to build a 10-lane bridge instead, is to take office on November 20 and has said it will review the project and its alternatives. The outgoing government has been asked to make no new tunnel-specific commitments during the transition, and the Ministry has said none will be made.

  • November 19 and 20, 2026: MLAs and the new cabinet scheduled to be sworn in (per news reports)
  • Incoming government's review of the tunnel project and alternatives (no timeline given)
  • Environmental Assessment Office review of the tunnel, which the Province expected to conclude before the end of 2026
  • Selection of contractors for the first two work packages, which the Province expected by early 2027

The tunnel today

Vehicles a day
82,200 (2025); 84,300 (2019)
Lanes
4 (3 in the peak direction and 1 the other way during counterflow)
Length
629 metres
Rush-hour speed
About 30 km/h today; 80 km/h expected with the new tunnel
Earthquakes
Does not meet current seismic standards; $22.5 million phase 1 retrofit done 2004 to 2006
Live drive times through the tunnel

The price tag, plan by plan

Each bar is what that plan was priced at when it was announced. Dollars of the day, not adjusted for inflation.

  • The tunnel itself Built

    Mar 1957 to May 23, 1959

    $16.6M

    4 lanes · Tunnel · What it cost to build, in 1959 dollars

  • 10-lane bridge Cancelled

    Sep 20, 2013 to Dec 17, 2018

    $3.5B

    10 lanes · Bridge · $66M spent (the Province's figure in September 2017, plus about $25M by BC Hydro to move a power line)

  • 8-lane tunnel, 2021 budget Revised

    Aug 18, 2021 to Jul 6, 2026

    $4.15B

    8 lanes · Tunnel · To open in 2030. An 8-lane bridge was priced at $4.22B and not chosen

  • 8-lane tunnel, 2026 budget Under way

    Jul 6, 2026 to now

    $8.5B

    8 lanes · Tunnel · $581M spent (to June 30, 2026, the last official report)

  • 10-lane bridge pledge Proposed

    Oct 15, 2026 to now

    $6B

    10 lanes · Bridge · The Conservative Party's figure; no costing has been published

Spent on the new tunnel so far

From the Province's own status reports. No newer figure has been published since June 2026.

  1. $108MSep 2024
  2. $197MDec 2024
  3. $288MJun 2025
  4. $398MDec 2025
  5. $480MMar 2026
  6. $581MJun 2026

The whole story

53 moments, oldest first. Pick a colour to follow one thread: only the reversals, only the money.

  1. PlansBC Liberal (Premier Christy Clark)

    Province chooses a new bridge, construction to start in 2017

    The Province announced the tunnel would be replaced by a new bridge on the existing Highway 99 corridor, with construction to begin in 2017.

    BC Gov News, release 2013PREM0095 (Sept. 20, 2013)

  2. MoneyBC Liberal (Premier Christy Clark)

    Project definition report: $3.5B, 10-lane toll bridge

    Transportation Minister Todd Stone released the project definition report and business case for a 10-lane bridge about 3 km long, three new interchanges and Highway 99 widening, estimated at $3.5 billion and funded by tolls.

    $3.5Bestimate (10-lane bridge)

    BC Gov News, release 2015TRAN0181 (Dec. 16, 2015)

  3. ReversalsBC NDP (Premier John Horgan)

    New government cancels bridge procurement, orders review

    The Province cancelled the procurement for the bridge and announced an independent technical review. It said it had spent approximately $66 million on the project, BC Hydro about $25 million on moving a transmission line, and that each of the two final bidding teams would be paid up to $2 million.

    $66MAbout $66M spent by the Province to Sept. 2017 (plus about $25M by BC Hydro)

    BC Gov News, Government to conduct independent review to find best solution for George Massey corridor (Sept. 6, 2017)

  4. BuiltBC NDP (Premier John Horgan)

    Preload sand remains beside Highway 99

    The Ministry said sand placed to compress soil for the bridge would stay until about the end of 2018 and then be reused. Global News reported the sand and new ditches cost $17 million.

    $17Mfor sand preload and ditches (as reported by Global News)

    As reported in the news; not from an official record.

    Global News, Sept. 19, 2018 (sand piles on Highway 99)

  5. ReversalsBC NDP (Premier John Horgan)

    Review released; 10-lane bridge will not proceed

    The Province released the independent review, which found six or eight lanes would handle most forecast traffic and that an immersed tube tunnel could be cost-competitive with a bridge. The Province said it would consult the region and prepare a new business case by fall 2020, and committed about $40 million for interim tunnel safety work.

    $40Minterim safety improvements to the existing tunnel

    Global News, Dec. 17, 2018 (Massey Tunnel report released)Province of BC, Independent Technical Review of the George Massey Crossing, presentation (Dec. 2018)Province of BC / TI Corp, George Massey Crossing technical briefing (Aug. 18, 2021)

  6. PlansBC NDP (Premier John Horgan)

    Metro Vancouver task force recommends 8-lane immersed tube tunnel

    A task force of Metro Vancouver mayors and councillors chose an eight-lane immersed tube tunnel, with two lanes for transit, from six options.

    Global News, Oct. 2, 2019 (task force recommendation)

  7. PoliticsBC NDP (Premier John Horgan)

    BC Liberals pledge to build the 10-lane bridge if elected

    During the 2020 provincial election campaign, BC Liberal leader Andrew Wilkinson pledged to replace the planned eight-lane tunnel with a 10-lane bridge. The NDP won the election.

    As reported in the news; not from an official record.

    Rock to Road (CBC News copy), Oct. 6, 2020

  8. PlansBC NDP (Premier John Horgan)

    Steveston interchange and Highway 99 transit works announced

    The Province announced a new five-lane Steveston interchange, more bus-on-shoulder lanes, a bus-only connection at Bridgeport Road and cycling upgrades, to be built ahead of the crossing. Budgets given in August 2021: Steveston $88 million, bus-on-shoulder $36 million, Highway 17A off-ramp $7 million, Bridgeport ramp $6 million.

    $137Mfor four corridor projects (2021 budgets)

    BC Gov News, New interchange, Highway 99 improvements to relieve traffic congestion (June 22, 2021)Province of BC / TI Corp, George Massey Crossing technical briefing (Aug. 18, 2021)

  9. MoneyBC NDP (Premier John Horgan)

    Province approves 8-lane tunnel: $4.15B, opening 2030

    The Province announced a toll-free, eight-lane immersed tube tunnel with two transit lanes and a separated cycling and walking path, estimated at $4.15 billion with opening in 2030. The eight-lane bridge alternative was estimated at $4.22 billion.

    $4.15Bestimate (8-lane tunnel)

    BC Gov News, release 2021TRAN0124 (Aug. 18, 2021)Province of BC / TI Corp, George Massey Crossing technical briefing (Aug. 18, 2021)

  10. MilestonesBC NDP (Premier John Horgan)

    Environmental assessment begins for the new tunnel

    The initial project description for the Fraser River Tunnel Project was filed with the B.C. Environmental Assessment Office. The detailed project description followed on May 10, 2023.

    TI Corp, Fraser River Tunnel Project Monthly Status Report, June 2026

  11. PoliticsBC NDP (Premier John Horgan)

    BC Liberals mark the bridge's planned opening date

    BC Liberal leader Kevin Falcon held a mock ribbon cutting, saying the 10-lane bridge would have opened that month, and said he would return to the bridge if tunnel construction had not begun by the 2024 election. Premier John Horgan defended the tunnel plan.

    Global News, Sept. 7, 2022 (BC Liberals mock ribbon cutting)

  12. MilestonesBC NDP (Premier David Eby)

    Three teams shortlisted to design and build the tunnel

    Cross Fraser Partnership, Daewoo-GS JV and Fraser River Tunnel Constructors were invited to submit proposals. The estimate remained $4.15 billion.

    $4.15Bestimate (8-lane tunnel)

    BC Gov News, release 2023MOTI0161 (Oct. 18, 2023)

  13. TrafficBC NDP (Premier David Eby)

    Counterflow system upgrade begins

    The electronic lane-control system was taken offline for four weeks for an upgrade, with crews setting up counterflow manually. Overnight tunnel closures were scheduled for April 4 to 8, 2024.

    BC Gov News, release 2024MOTI0024 (March 5, 2024)

  14. MilestonesBC NDP (Premier David Eby)

    Cross Fraser Partnership named preferred proponent

    The Province selected Cross Fraser Partnership (Bouygues, FCC, Pomerleau and Arcadis) for the design and early works phase. Major construction was scheduled for 2026 and opening for 2030.

    BC Gov News, release 2024MOTI0092 (July 23, 2024)

  15. PoliticsBC NDP (Premier David Eby)

    BC election: NDP re-elected with 47 of 93 seats

    The BC NDP under David Eby won 47 seats, the Conservative Party of BC 44 and the Greens 2. The tunnel project continued.

    Wikipedia, 2024 British Columbia general election

  16. BuiltBC NDP (Premier David Eby)

    Early construction begins on the tunnel site

    Tree clearing started on Deas Island in January 2026, followed by utility relocation and preparation for jetties, a temporary trestle bridge and the casting basin where tunnel sections will be built.

    Highway 99 Tunnel Program newsletter, Early Construction Works Begin (Jan. 2026)Highway 99 Tunnel Program, Early Construction WorkBC Gov News, Construction continues on Fraser River Tunnel Project with federal partnership (July 6, 2026)

  17. MoneyBC NDP (Premier David Eby)

    B.C. Budget 2026: tunnel cost and schedule under review

    The provincial budget left the project cost unchanged, at about $4.3 billion including the highway corridor works ($4.15 billion for the tunnel itself), and said the budget and schedule would be updated once talks with the contractor finished.

    $4.15Btunnel estimate, stated as under review

    As reported in the news; not from an official record.

    Daily Hive, Feb. 20, 2026 (B.C. budget and the tunnel's cost and timeline)TI Corp, Fraser River Tunnel Project Monthly Status Report, March 2026

  18. ReversalsBC NDP (Premier David Eby)

    Province moves to end agreement with Cross Fraser Partnership

    On June 15, 2026 the Province said it was exercising a termination option, after the two sides did not agree on commercial terms for final construction. The remaining work was split into five packages, with requests for qualifications for the first two issued on June 16. Cross Fraser Partnership kept delivering the early works.

    Indo-Canadian Voice (provincial release text), June 15, 2026Engineering News-Record, June 18, 2026TI Corp, Fraser River Tunnel Project Monthly Status Report, June 2026

  19. MoneyBC NDP (Premier David Eby)

    Tunnel project spending reaches $580.7M

    The June 2026 status report gave total project spending to date of $580.7 million, including $37.5 million in June. This is the latest published figure.

    $581Mspent on the tunnel project to June 30, 2026

    TI Corp, Fraser River Tunnel Project Monthly Status Report, June 2026

  20. MoneyBC NDP (Premier David Eby)

    Ottawa commits up to $3B to the tunnel replacement

    Prime Minister Mark Carney and Premier David Eby announced the Canada-British Columbia Cooperative Prosperity Agreement, which includes up to $3 billion in federal funding for the tunnel replacement.

    $3BUp to $3B federal contribution

    Prime Minister of Canada, Canada-British Columbia Cooperative Prosperity Agreement (July 2, 2026)BC Gov News, Construction continues on Fraser River Tunnel Project with federal partnership (July 6, 2026)

  21. PoliticsBC NDP (Premier David Eby)

    Provincial election called

    Premier David Eby called an election for October 24, 2026, two years ahead of the fixed date. Lorne Doerkson had become interim leader of the Conservative Party of BC on September 20.

    As reported in the news; not from an official record.

    Wikipedia, 2026 British Columbia general election

  22. PoliticsBC NDP (Premier David Eby)

    Conservatives pledge 10-lane bridge instead of the tunnel

    Conservative leader Lorne Doerkson said his party would cancel the eight-lane tunnel and build a 10-lane bridge. NDP leader David Eby said the change would delay the crossing. Two construction unions opposed it, and one, IUOE Local 115, said $581 million had been spent as of June.

    Conservative Party of BC, news release (Oct. 15, 2026)North Delta Reporter, Oct. 15, 2026

  23. MoneyBC NDP (Premier David Eby)

    Doerkson puts the bridge at $6B

    Lorne Doerkson said the party believed a bridge could be built for $6 billion, about $2.5 billion less than the tunnel budget. News reports in November said the party had not published a costing.

    $6B(Conservative Party estimate for a 10-lane bridge; no costing published)

    As reported in the news; not from an official record.

    The Link Paper, Nov. 13, 2026 (Farnworth statement)Vancouver Sun via Yahoo News Canada, Nov. 12, 2026Maple Ridge News (Black Press), Nov. 12, 2026

  24. PoliticsTransition: BC NDP caretaker government (Premier David Eby); Conservative Party of BC government-elect (Premier-designate Lorne Doerkson)

    Federal minister: Ottawa will back a bridge or a tunnel

    Federal Transport Minister Steven MacKinnon said in Delta that Ottawa supports "crossing that river, whatever way the Premier tells us to." Whether the $3 billion would carry over to a bridge has not been confirmed.

    Daily Hive, Nov. 1, 2026 (federal position on a bridge)Global News, Nov. 12, 2026

  25. PoliticsTransition: BC NDP caretaker government (Premier David Eby); Conservative Party of BC government-elect (Premier-designate Lorne Doerkson)

    Doerkson asks outgoing government to pause tunnel-only work

    Premier-designate Lorne Doerkson asked that no new contracts or commitments specific to the tunnel be made during the transition, pending a review of the project and alternatives, and said existing contracts would be respected. Outgoing minister Mike Farnworth called the request an attempt to shift the cost of the bridge promise; the Ministry said no new commitments would be made under the caretaker convention.

    The Link Paper, Nov. 13, 2026 (Doerkson statement)Global News, Nov. 12, 2026Vancouver Sun via Yahoo News Canada, Nov. 12, 2026The Link Paper, Nov. 13, 2026 (Farnworth statement)

  26. PoliticsTransition: BC NDP caretaker government (Premier David Eby); Conservative Party of BC government-elect (Premier-designate Lorne Doerkson)

    New cabinet scheduled to be sworn in

    News reports say Conservative MLAs are to be sworn in on November 19 and Lorne Doerkson and his cabinet on November 20, 2026. No deadline has been given for the incoming government's review of the crossing.

    As reported in the news; not from an official record.

    Daily Hive, Nov. 12, 2026Maple Ridge News (Black Press), Nov. 12, 2026Vancouver Sun via Yahoo News Canada, Nov. 8, 2026

Checked Nov 14, 2026. Every entry links to its source: provincial news releases and status reports first, then news reports where there is no official record. Spotted something wrong? Tell us.